Comments on: How to Complete an Input Map in a Lean Six Sigma Project https://sixsigmadsi.com/how-to-complete-the-input-or-variables-map/ Six Sigma Development Solutions, Inc., providing “Operational Excellence” to Organizations around the Globe. Tue, 04 Jul 2023 20:09:46 +0000 hourly 1 https://wordpress.org/?v=6.6.2 By: Kevin Clay https://sixsigmadsi.com/how-to-complete-the-input-or-variables-map/#comment-50221 Mon, 09 Sep 2019 22:54:52 +0000 https://sixsigmadsi.com/wordpress/?p=333#comment-50221 In reply to henry.

Henry, The Outputs would be the measurable outputs from each decision. Remember that the goal of an input map is to track the inputs to a process so we can Pareto those inputs in the C&E Matrix and then determine their Failure Modes in the FMEA. The Input Map doesn’t care about the actual decision being made as would a process flow map.

]]>
By: henry https://sixsigmadsi.com/how-to-complete-the-input-or-variables-map/#comment-49869 Sun, 08 Sep 2019 18:46:50 +0000 https://sixsigmadsi.com/wordpress/?p=333#comment-49869 In the Final Assy step, what will be the output in case of a decision point is present?

For example, if I have these steps:

1. Setup
2. Apply the peanut butter
3. Apply the Jelly
4. Final Assy
5. Pass sandwich to customer

The step number 5 has a decision point: the customer may require a slice sandwich into 2 halves or not. When making the input map, what is the output in the step number 5?

]]>